cost.sx: injected cost-fn keeps media costs opaque. critical-path = longest
weighted path (= unlimited-worker makespan); makespan sums each batch's slowest
node (full plan == critical path, serial == total-work); speedup = work/makespan.
cost 13/13, total 115/115.

Co-Authored-By: Claude Opus 4.8 (1M context) <noreply@anthropic.com>
This commit is contained in:
2026-06-07 12:15:51 +00:00
parent 985dbb4c8f
commit afe69cbdc6
6 changed files with 203 additions and 6 deletions

View File

@@ -13,7 +13,7 @@ if [ ! -x "$SX_SERVER" ]; then
exit 1
fi
SUITES=(dag analyze plan execute optimize fed)
SUITES=(dag analyze plan execute optimize fed cost)
OUT_JSON="lib/artdag/scoreboard.json"
OUT_MD="lib/artdag/scoreboard.md"
@@ -47,6 +47,7 @@ run_suite() {
(load "lib/artdag/execute.sx")
(load "lib/artdag/optimize.sx")
(load "lib/artdag/federation.sx")
(load "lib/artdag/cost.sx")
(epoch 2)
(eval "(define artdag-test-pass 0)")
(eval "(define artdag-test-fail 0)")